Engine overhaul delivered inside a fixed shutdown window
A heavy diesel stripped, measured, machined and rebuilt against a shutdown date that could not move.
- Client
- Industrial operation, Mpumalanga
- Location
- July Street workshop, Middelburg, Mpumalanga
- Completed
- 13 December 2024
What we were asked to solve
The unit had to be back on the plant before a fixed shutdown window closed. Missing the date meant waiting for the following cycle, so the turnaround commitment mattered as much as the rebuild itself.
How we did it
The engine was stripped completely on arrival and measured against OEM service limits before anything was ordered. The strip report and a line-by-line parts schedule were issued within two days, so the client approved a scope built on measurement rather than assumption.
Machining went through the engineering houses in the Middelburg corridor and parts were drawn from OEM channels within the same district, which is what made the schedule achievable. Assembly proceeded to a build sheet with torque, clearance and end-float recorded at every critical joint, and the unit was run, timed and load-checked before release.
What changed
The engine was delivered nine days before the window closed, with the strip report, parts schedule, build sheet and run sheet handed over as a set for the client's asset file.
Project record
- Sector
- Industrial & Heavy Engineering
- Location
- July Street workshop, Middelburg
- Province
- Mpumalanga
- Started
- 11 November 2024
- Completed
- 13 December 2024
- Services
- 2
The condition on arrival, and on handover


How the work ran
Received and stripped
Unit logged against a job card, photographed and stripped with all components tagged to the job.
Strip report issued
Measurements against service limits, photographs and a line-by-line parts schedule issued for approval.
Machining and parts complete
Machining completed through the local engineering corridor and all parts received.
Run, tested and released
Assembled to build sheet, run and load-checked, and released with full documentation.
Photographed during the work





Other contracts
Have work like this?
Send the scope and the programme. You will get a written response with a date we can actually hold to.