Main haul route rebuilt and placed under standing maintenance

A deteriorating primary haul route rebuilt to a layer design, then held under a standing grader and water circuit.

Client
Coal producer, Mpumalanga
Location
Middelburg district, Mpumalanga
Completed
21 June 2024
4.2 kmRoute rebuilt
16 weeksProgramme
Standing circuitMaintenance
2Rain seasons held
The brief

What we were asked to solve

The operation's main haul route had been patched rather than maintained for several seasons. Cross-fall had flattened, the wearing course was gone in the wheel paths, and standing water after rain was cutting the surface faster than it could be repaired. Tyre spend was climbing and cycle times had drifted well off the planning assumption.

Approach

How we did it

We proof-rolled the existing subgrade and cut out the soft areas rather than building over them, then placed and compacted a selected layer and a new wearing course to design thickness. Cross-fall was reinstated across the full length and table drains were cut on both sides with mitre drains discharging clear of the formation.

Once the road was handed over, it went onto a standing maintenance circuit — grader passes on an agreed frequency and a water bowser circuit with application rates set for the gradient rather than applied uniformly.

Outcome

What changed

The route has held its profile through two rain seasons. Defects are cut out at the weekly grader pass instead of being allowed to propagate, and the maintenance circuit continues under a rolling contract.

Project record

Sector
Mining & Open-Cast
Location
Middelburg district
Province
Mpumalanga
Started
4 March 2024
Completed
21 June 2024
Services
3
Programme

How the work ran

Each milestone carried a deliverable the client signed before the next stage started.
  1. Survey and layer design

    Existing route surveyed, subgrade proof-rolled and the layer design set against the largest vehicle on the route.

  2. Subgrade correction

    Soft areas excavated and replaced with selected material, compacted to the specified density.

  3. Wearing course and drainage

    Wearing course placed to design thickness, cross-fall trimmed and table and mitre drains cut.

  4. Handover and maintenance start

    Route handed over on as-built survey and the standing grader and water circuit commenced.

On site

Photographed during the work

An articulated water bowser truck parked beside a service vehicle on a haul road
A freshly refurbished Caterpillar D10T dozer standing on rock at a mine site
Two large tracked excavators positioned on a coal bench at an open-cast mine under heavy cloud